Project Description

The project involved the demolition and removal of an existing clarifier, design and construct of a replacement sludge thickener. This required extensive dewatering and installation of piles to prevent uplift, refurbishment of 2 new additional clarifiers, new backwash detention tank and all associated pipeworks, electrical works, control systems, roadworks as well as commissioning of the upgrade

 

Project Details

Client: Unity Water
Contract system:Design & Construct
Contract sum:$4.0 Million 
Completion date:

 September 2014