PROJECT DESCRIPTION

 The Design and Construct of pre and post lime dosing system and other works. This project includes lime handling systems incorporating  major piling and earthworks, ancillary building upgrades for both pre and post lime systems, pipe work, 100 tonne lime silo, lime saturator, lime water holding tank, dosing pumps, post lime sludge pumps, booster pumps, associated electrical works, an acid dosing system and the associated commissioning and training.

PROJECT DETAILS

Client: SEQ Water
Contract system:Design and Construct
Contract sum:$5.6 Million 
Completion date:November 2016