21/06/2016
The landers Shute WTP’s existing screw presses needed to be replaced, with Stirloch awarded the project to upgrade the plants sludge management system. The project included the installation of 2 new centrifuges into the existing sludge building, requiring the careful staging and removal of the existing presses to ensure SEQ water maintained the ability to de-sludge during the peak x/mas period. The building is to be extensively upgraded and extended to accommodate the new centrifuges, conveyors and Switchroom. Other works included a new sludge holding tank, upgrading to the existing thickeners associated pipework’s and pump upgrades including all electrical and control systems