PROJECT DESCRIPTION

The purpose of this Contract is for the supply, installation, testing and commissioning of a new 36ML reinforced concrete reservoir within the footprint of the decommissioned Basin No.2.

The scope includes:

  • Demolition works including removal of existing inlet, outlet, scour and overflow pipework associated with Basin No.2 and associated concrete structures and removal of a level monitoring bridge and other miscellaneous works;
  • Bulk earthworks including removal of embankments, construction of a lime stabilised capping layer, placement of fill around the reservoir, roadworks, drainage and construction of a stormwater detention basin;
  • New pipelines to divert water into the reservoir, overflow pipework, scour pipework and an outlet main, including cut-ins and connections to the existing pipes;
  • Civil and structural works associated with the new reservoir; and
  • Electrical and instrumentation works for the new reservoir including all conduits and pits.

PROJECT DETAILS

Client East Gippsland Water
Project location Wy Yung, Victoria
Contract system Construct
Reservoir capacity 36 ML
Contract sum $10.9 million
Completion date Due: January 2021