Stirloch Logo cropped 2
Queensland
+61 7 3393 2860

Blind Bight WWTP Upgrade

PROJECT DESCRIPTION

Construction of new 1ML/day IDEA plant, which incorporate the construction of inlet works, reactors, pump stations, mixing tanks dosing systems, operation building, site works electrical, mechanical, process control works and commissioning of the plant.

PROJECT DETAILS

Client South East Water
Project location Blind Bight, Victoria
Contract system Construct Only
Contract sum $3.9 Million
Completion date 2002
© 2014 | Site Map | Web Design Brisbane by iFactory