Southbank Storm Water Harvest Scheme (Brisbane, Qld)

PROJECT DESCRIPTION

Design and construct of the storm water harvest scheme at Southbank Parklands in Brisbane. The project involves the use of the existing building, design and construct of a 2 ML underground storage facility, including sheet piling and a 30 metre deep timber piles, water treatment plant, pump station, upgrade of the parks landscape network and associated landscaping.

 

PROJECT DETAILS

Client Southbank Corporation
Project location Southbank, Brisbane, Queensland
Contract system Design & Construct
Contract sum $8.4 Million
Completion date March 2011